Question: The following table relates to a project. Complete a network diagram and answer the following questions 1. The critial path is 1. B-D-G-H 2.C-E-F-H 3.A-D-F-H
The following table relates to a project.

Complete a network diagram and answer the following questions 1. The critial path is 1. B-D-G-H 2.C-E-F-H 3.A-D-F-H 4. A-D-F-H refer to the resource chart you completed The slack for activity E is 1. 0 days 2. 1 day 3. 3 days 4. 2 days Refer to the resource chart you completed Activity D is an example of 1. merge activity only 2. Burst activity only 3. Combination activity 4.Merge and bust activity The late finish for activity C is 1.6 2.16 3.13 4.7
\begin{tabular}{|c|c|c|} \hline Activity & ImmediatePredecessor/s & Duration (Days) \\ \hline A & - & 5 \\ B & - & 6 \\ C & - & 5 \\ D & A,B,C & 7 \\ E & A,C & 9 \\ F & D,E & 5 \\ G & C,D & 8 \\ H & F, G & 11 \\ \hline \end{tabular}