Question: The following table represents a plan for a project code named Prometheus. The project plan consists of 11 activities code named P1 thru P11. The
The following table represents a plan for a project code named Prometheus. The project plan consists of 11 activities code named P1 thru P11. The activity times - optimistic a, pessimistic b, and most likely m - and their precedence relationships in the table below.
|
| Predecessor Activities | Time In Days | ||
| Activities | a | m | b | |
| P1 | - | 2 | 3 | 4 |
| P2 | P1 | 1 | 2 | 3 |
| P3 | P1 | 4 | 5 | 12 |
| P4 | P1 | 3 | 4 | 11 |
| P5 | P2 | 1 | 3 | 5 |
| P6 | P3 | 1 | 2 | 3 |
| P7 | P4 | 1 | 8 | 9 |
| P8 | P5, P6 | 2 | 4 | 6 |
| P9 | P8 | 2 | 4 | 12 |
| P10 | P7 | 3 | 4 | 5 |
| P11 | P9, P10 | 5 | 7 | 8 |
a) Construct the project network diagram. Make sure the diagram includes all the elements - early start, early finish, late start, late finish, and activity code name & time.
b) Indicate the critical path. What is the expected completion time of Prometheus? c) What is the probability that the project will take more than 30 days to complete?