Question: The following table represents a plan for a project code named Prometheus. The project plan consists of 11 activities code named P1 thru P11. The

The following table represents a plan for a project code named Prometheus. The project plan consists of 11 activities code named P1 thru P11. The activity times - optimistic a, pessimistic b, and most likely m - and their precedence relationships in the table below.

Predecessor Activities

Time In Days

Activities

a

m

b

P1

-

2

3

4

P2

P1

1

2

3

P3

P1

4

5

12

P4

P1

3

4

11

P5

P2

1

3

5

P6

P3

1

2

3

P7

P4

1

8

9

P8

P5, P6

2

4

6

P9

P8

2

4

12

P10

P7

3

4

5

P11

P9, P10

5

7

8

a) Construct the project network diagram. Make sure the diagram includes all the elements - early start, early finish, late start, late finish, and activity code name & time.

b) Indicate the critical path. What is the expected completion time of Prometheus? c) What is the probability that the project will take more than 30 days to complete?

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!