Question: the following table represents a plan for a project: Time (days) job no. Predecessor Job(s). a m b A - 2 4 7 B A
the following table represents a plan for a project:
Time (days)
job no. Predecessor Job(s). a m b
A - 2 4 7
B A 1 4 9
C A 3 6 9
D B,C 2. 3 5
E B 1 3 9
F C,D 2 4 5
G E 3 8 10
H E,F 1 2 3
I G,H 3 5 7
a) construct the appropriate network diagram
b) indicate the critical path
c) what is the expected completion time for the project
d) what is the probability it will take longer than 26 days?