Question: the following table represents a plan for a project: Time (days) job no. Predecessor Job(s). a m b A - 2 4 7 B A

the following table represents a plan for a project:

Time (days)

job no. Predecessor Job(s). a m b

A - 2 4 7

B A 1 4 9

C A 3 6 9

D B,C 2. 3 5

E B 1 3 9

F C,D 2 4 5

G E 3 8 10

H E,F 1 2 3

I G,H 3 5 7

a) construct the appropriate network diagram

b) indicate the critical path

c) what is the expected completion time for the project

d) what is the probability it will take longer than 26 days?

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!