Question: The following table represents event precedence constraints and expected activity times for a set of activities: Expected Activity Time (hours) 3 2 1 Activity A->B

The following table represents event precedence

The following table represents event precedence constraints and expected activity times for a set of activities: Expected Activity Time (hours) 3 2 1 Activity A->B A->C B -> D B -> E C -> D C -> F D -> E D -> F E-> G F-> G 15 2 16 3 2 14 1 What is the critical path of the network diagram? O A. [A-> C -> F-> G] O B. [A-> B -> E->G] O C. [A-> B -> D -> E->G] O D.(A -> C -> D -> E -> G]