Question: The following table shows a WBS with 11 tasks. Note that each task has an ID, a description, duration, and a reference to predecessor tasks,

The following table shows a WBS with 11 tasks. Note that each task has an ID, a description, duration, and a reference to predecessor tasks, if any, which must be completed before the task can begin. Construct a PERT/CPM chart from these tasks (similar to chart in Slide 20 Ch 3). Also, identify the critical path for this project (what are the tasks on the critical path and how long would it take?).

Task No.

Description

Duration (Days)

Predecessor Tasks

1

Develop Plan

1

-

2

Assign Tasks

4

1

3

Obtain Hardware

17

1

4

Programming

60

2

5

Install Hardware

10

3

6

Program Test

25

4

7

Write User Manual

25

5

8

Concert Files

15

5

9

System Test

25

6

10

User Training

20

7,8

11

User Test

25

9,10

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!