Question: The following table shows orders to be processed at a machine. LO 3 Job Processing Time ( days ) Due Date ( days ) a

The following table shows orders to be processed at a machine. LO3
Job
Processing
Time (days)
Due Date
(days)
a. Determine the processing sequence using each of these priority rules:
(1) CR,(2) MST,(3) SPT,(4) EDD.
b. Determine the performance of each rule using (1) average flow time,
(2) average days late.
c. Is one rule superior to the others?
A 820
B 1018
C 525
D 1117
E 935