Question: The following table shows the summary activities for a construction project. Assuming that one month is equal to 4 weeks, answer the following questions:

The following table shows the summary activities for a construction project. Assuming that one
month is equal to 4 weeks, answer the following questions:\table[[Activity,IPA,Duration (weeks),Direct cost ($)],[A,-,3,45,000],[B,A(SS+1W),7,140,000],[C,A(FS-1W),6,132,000],[D,C(FS),2,100,000],[E,C(SS+2), B(FF+3),3,45,000],[F,E (FS), D(FF),5,30,000],[G,E(FS),1,8,000]]A. Assuming that the project overhead is estimated to be $45,000 and the yearly general
overhead for the contractor is estimated to be $1,000,000. If the contractor distributes the
yearly general overhead over eight projects, the total direct cost is $20,000,000. Draw the
expense curve (S-curve) for the project.B. Assume that the contractor is willing to use 20% profit (from the total cost) for this project.
Also, the contractor plans to submit his progress payment to the client at the end of each
month. Upon approval, the owner will deduct 10% for retainage (retention) and pay the
contractor one month later. The accumulated retainage will be paid with the last payment.
Calculate and draw the income profile (flow chart) and shade the overdraft area. (8/%)
 The following table shows the summary activities for a construction project.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Accounting Questions!