Question: The following time-phasing chart is available for a single item within a MRP system. chart by estimating inventory on hand and planned order release values.
The following time-phasing chart is available for a single item within a MRP system. chart by estimating inventory on hand and planned order release values. Lead time is 2 weeks and order policy is 100 units, which means this part can be ordered only in 100-unit batches. Inventory replenishment is JIT, lead times are negligible. Week Number 1 2 3 4 5 6 7 8 9 10 Gross Requirements 80 95 110 50 Scheduled Receipt 100 Inventory on Hand Planned Order Release
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
