Question: The following unbalanced assignment problem is given. Change the problem into a balanced problem and then solve the problem. What is the total cost of

The following unbalanced assignment problem is given. Change the problem into a balanced problem and then solve the problem.

What is the total cost of the optimal solution?

 
Machine A
Machine B
Machine C
Job 1
$13
$13
$15
Job 2
$16
$15
$14
Job 3
$11
$13
$20
Job 4
$18
$10
$15

$36

$34

$33

$32

$35