Question: The Gantt chart is selected as the appropriate graphical tool. SOLUTION Processing Unscheduled Center not available (e.g., maintenance time, repairs, shortages) INSIGHI The four work
The Gantt chart is selected as the appropriate graphical tool. SOLUTION Processing Unscheduled Center not available (e.g., maintenance time, repairs, shortages) INSIGHI The four work centers process several jobs during the week. This particular chart indicates that the metalworks and painting centers are completely loaded for the entire week. The mechanical and electronic centers have some idle time scattered during the week. We also note that the metalworks center is unavailable on Tuesday, and the painting center is unavailable on Thursday, perhaps for preventive maintenance. LEARNING EXERCISE What impact results from the electronics work center closing on Tuesday for preventive maintenance