Question: The grid averaging method is used to estimate rough grading in a project. The existing elevations at the four corners of a 25x25 grid are:
The grid averaging method is used to estimate rough grading in a project. The existing elevations at the four corners of a 25x25 grid are: 86.67, 87.33' 87.67 and 88.33. If the design (i.e. proposed) rough grade level is 86, what is the quantity of cut/fill in this grid? 34.72 BCY O 57.87 BCY 57.87 CCY 34.72 CCY