Question: The gross requirements for items A and B are specified for weeks 1 through 12 in the tables that follow. The product structure for each
The gross requirements for items A and B are specified for weeks 1 through 12 in the tables that follow. The product structure for each of the two items is given in two figures in which the lead time for each item and constituent part is specified within brackets.
Product Structure for items A and H
| Item A, Level 0 | ||||||||||||
|
| 01 | 02 | 03 | 04 | 05 | 06 | 07 | 08 | 09 | 10 | 11 | 12 |
| Gross requirements. | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 50 | 0 | 50 | 0 | 50 |
| Planned order release | ? | ? | ? | ? | ? | ? | ? | ? | ? | ? | ? | ? |
| Item H, Level 0 | ||||||||||||
|
| 01 | 02 | 03 | 04 | 05 | 06 | 07 | 08 | 09 | 10 | 11 | 12 |
| Gross requirements. | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 80 | 60 | 40 | 20 |
| Planned order release | ? | ? | ? | ? | ? | ? | ? | ? | ? | ? | ? | ? |
| Item C, Level 1 | ||||||||||||
|
| 01 | 02 | 03 | 04 | 05 | 06 | 07 | 08 | 09 | 10 | 11 | 12 |
| Gross requirements. | ? | ? | ? | ? | ? | ? | ? | ? | ? | ? | ? | ? |
| Planned order release | ? | ? | ? | ? | ? | ? | ? | ? | ? | ? | ? | ? |
Determine the planned order releases for item C, and then select the correct number of units for the planned order release in specified weeks:
|
|
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts