Question: The indirect costs for each project duration are given below: Project 18 17 16 15 Duration (days) Indirect 400 350 300 250 Cost ($) Find


The indirect costs for each project duration are given below: Project 18 17 16 15 Duration (days) Indirect 400 350 300 250 Cost ($) Find the optimum cost time schedule for the project. 14 200 (9) 13 150 4 The indirect costs for each project duration are given below: Project 18 17 16 15 Duration (days) Indirect 400 350 300 250 Cost ($) Find the optimum cost time schedule for the project. 14 200 (9) 13 150 4