Question: The information about a project with 10 activities is shown below. Activity A; 26 days; IP = none Activity B: 24 days; IP = none

The information about a project with 10
The information about a project with 10 activities is shown below. Activity A; 26 days; IP = none Activity B: 24 days; IP = none Activity C; 31 days; IP = A Activity D: 27 days; IP = A,B Activity E; 36 days; IPB Activity F: 31 days; IP = C, D Activity G: 28 days: IP =CD Activity H; 27 days; IP - E Activity K: 25 days; IP-F Activity M: 21 days: IP - GH The latest start time of activity D is at the end of day