Question: The initial precedence diagram for a small construction project is shown below with its planned activity times. At the end of the 1 2 th

The initial precedence diagram for a small construction project is shown below with its
planned activity times. At the end of the 12th day, the field progress report gives you
the following information:
- Activity {A} was completed on schedule.
- Activity {C} was completed one day earlier.
- The duration of activity {B} is 10 days instead of 6 days.
- Activity {D} started as planned but five days were lost due to waiting for the
resources.
- Activity {Y} cannot start before the end of the 36th day.
- The duration of activity {H} will be reduced to 7 days instead of 17 days.
- Activity {Z} is expected to take an additional two days.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!