Question: The initial AON diagram for a small engineering project is shown below with its planned activity times in days. At the end of the 1
The initial AON diagram for a small engineering project is shown below with its planned activity times in days. At the end of the day, the field progress report gives you the following information:
Activity A was completed on schedule.
Activity B started as planned but five days were lost due to waiting for the required resources.
Activity C was completed one day earlier.
The remaining duration of Activity is days.
The duration of activity H will be reduced to days instead of days.
Activity is expected to take three days more.
Due to owner requirement the volume of work of activity X will be increased by
Construct the updated AON diagram, calculate the early start and early finish times of each activity.
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock