Question: The initial AON diagram for a small engineering project is shown below with its planned activity times in days. At the end of the 1

The initial AON diagram for a small engineering project is shown below with its planned activity times in days. At the end of the 17th day, the field progress report gives you the following information:
Activity "A" was completed on schedule.
Activity "B" started as planned but five days were lost due to waiting for the required resources.
Activity "C" was completed one day earlier.
The remaining duration of Activity "D" is 2 days.
The duration of activity "H" will be reduced to 15 days instead of 17 days.
Activity "Z" is expected to take three days more.
Due to owner requirement the volume of work of activity " X " will be increased by 100%.
Construct the updated AON diagram, calculate the early start and early finish times of each activity.
 The initial AON diagram for a small engineering project is shown

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!