Question: The intersection of the Work Breakdown Structure ( WBS ) and Organisational Breakdown Structure ( OBS ) denotes: a . Two same - level deliverables.

The intersection of the Work Breakdown Structure (WBS) and Organisational Breakdown Structure (OBS) denotes:
a.
Two same-level deliverables.
b.
The parent organisation and the client.
c.
Upper-level deliverables and lower-level deliverables.
d.
Work packages and organisational units.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!