Question: The intersection of the Work Breakdown Structure ( WBS ) and Organisational Breakdown Structure ( OBS ) denotes: a . The parent organisation and the

The intersection of the Work Breakdown Structure (WBS) and Organisational Breakdown Structure (OBS) denotes:
a.
The parent organisation and the client.
b.
Work packages and organisational units.
c.
Two same-level deliverables.
d.
Upper-level deliverables and lower-level deliverables.