Question: The _ _ _ _ _ _ is the latest possible point in time when a schedule activity can be completed without violating schedule constraint
The is "the latest possible point in time when a schedule activity can be completed without violating schedule constraint or delaying the project end date."
a early start date ES
b late start date LS
c early finish date EF
d late finish date LF