Question: The _ _ _ _ _ _ is the latest possible point in time when a schedule activity can be completed without violating schedule constraint

The ______ is "the latest possible point in time when a schedule activity can be completed without violating schedule constraint or delaying the project end date."
a. early start date (ES)
b. late start date (LS)
c. early finish date (EF)
d. late finish date (LF)