Question: 1. The table below shows the relevant task data for a certain project, with durations given in days. a. Draw a fully analyzed network diagram

1. The table below shows the relevant task data

1. The table below shows the relevant task data for a certain project, with durations given in days. a. Draw a fully analyzed network diagram for the project showing all activity times, find the project duration, develop the activities boundary timetable, and identify the critical path. b. Assuming each task starts as soon as possible, construct the Gantt chart and corresponding resource loading diagram for the project. c. Construct a second resource loading diagram showing how the timing of individual tasks could be rearranged to reduce the fluctuation in worker demand, without changing overall project duration. d. If only 7 workers are available, how would you assign workers to tasks to ensure that the project can be completed without violating the resource limit? The project duration may be extended in this case if necessary. (15 points) Task Predecessor Duration Workers A 3 5 B 2 2 4 3 D B,C 3 2 E A 5 3 F D 3 4 - 2. The table below shows the relevant task data for a certain project, with durations given in weeks. The project progress information shown in the table was collected by the project manager at the end of the 4th week. a. Draw a fully analyzed network diagram for the project showing all activity times, find the project duration, develop the activities boundary timetable, and identify the critical path. b. Construct a Gantt chart for the project, assuming each task starts as soon as possible. c. Using proportional budget figures, determine the current cost, schedule, and time variances for the project. Also determine CPI, SPI, and CSI. Comment on the overall condition of the project at this point in time. (15 points) Activity Predecessor Duration Budget Cost Actual Cost % Complete A 1 $15,000 $14,000 100 B A 2 $12,000 $14,000 100 A 3 $36,000 $30,000 67 D B 4 $20,000 $12,000 50 E 2 $12,000 0

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!