Question: The _____ is used to systematically dismantle the project deliverable into its smallest components and organize these components into a logical sequence that allows components

The _____ is used to systematically dismantle the project deliverable into its smallest components and organize these components into a logical sequence that allows components to be built and assembled correctly.

network diagram

work breakdown structure

project scope statement

scope of work

Which one of the following is false about the information gathering?

The work breakdown structure is one of the primary sources of information

Who, What, and How are the three most important questions during information gathering phase

The last step in the identification of risks is the process of gathering and reviewing information of project work activities

It is key to understand what type of information is relevant and needs to be collected for review.

______ tool allows project managers to arrange work activities graphically in sequence and analyze the flow of work throughout the project lifecycle.

Network diagram

RBS

WBS

Gantt Chart

Generally speaking, ______ does not belong to activity information checklist.

total cost

total duration

project name

major risks

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!