Question: The Late Start (LS) time for Activity D Design Custom Parts is days. 2 3 12 15 Project Information for Homework #1 begin{tabular}{|c|l|c|c|} hline ID

The Late Start (LS) time for Activity D Design Custom Parts is days. 2 3 12 15 Project Information for Homework \#1 \begin{tabular}{|c|l|c|c|} \hline ID & \multicolumn{1}{|c|}{ Activity } & Predecessor & Time (Days) \\ \hline A & Order Review & None & 2 \\ \hline B & Order Standard Parts & A & 15 \\ \hline C & Produce Standard Parts & A & 10 \\ \hline D & Design Custom Parts & A & 13 \\ \hline E & Manufacturing Custom Hardware & C, D & 15 \\ \hline F & Assemble & B, E & 10 \\ \hline G & Test & F & 5 \\ \hline \end{tabular}