Question: 1. The Late Start (LS) time for activity B order Standard Parts is ___ days. 2. The Late finish (LF) time for activity d design
1. The Late Start (LS) time for activity B order Standard Parts is ___ days. 2. The Late finish (LF) time for activity d design custom parts is ___ days

Chapter 6 Homework The project information for the custom order project of the Air Control Company is presented below. Draw a project network for this project and answer the questions. ID Activity Predecessor Time (Days) A Order Review None 2 B Order Standard Parts A 15 C Produce Standard Parts A 10 D Design Custom Parts A 13 E Manufacturing Custom Hardware C, D 15 F Assemble B, E 10 G Test F 5