Question: The latest start time ( LS ) is _ _ _ _ _ _ _ _ _ _ . Answer the latest an activity can
The latest start time LS is
Answer
the latest an activity can be started and still finish the project on time, calculated by subtracting the activitys duration from its latest finish time
the earliest an activity can be started, as determined by the earliest finish time for all immediate predecessors
the difference between an activitys latest start time LS and earliest start time ES
the latest an activity can be finished and still finish the project on time, as determined by the latest start time for all immediate successors
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
