Question: The latest start time ( LS ) is _ _ _ _ _ _ _ _ _ _ . Answer the latest an activity can

The latest start time (LS) is __________.
Answer
the latest an activity can be started and still finish the project on time, calculated by subtracting the activitys duration from its latest finish time
the earliest an activity can be started, as determined by the earliest finish time for all immediate predecessors
the difference between an activitys latest start time (LS) and earliest start time (ES)
the latest an activity can be finished and still finish the project on time, as determined by the latest start time for all immediate successors