Question: The learning rate for a particular operation is 90%, and the first unit of production took 100 hours. What is the number of labor hours
The learning rate for a particular operation is 90%, and the first unit of production took 100 hours.
What is the number of labor hours required to produce the eighth (8th) unit?
Note: you should use the general equation for learning curves to do this problem:
- TN = T1 x Ln = Time required for the Nth unit, where:
- TN = unit cost or unit time of the Nth unit
- L = decimal learning curve rate (e.g., 0.9 for 90% learning rate)
- n = number of times T is doubled
Group of answer choices
- 81.0 hours
- 72.9 hours
- 41.0 hours
- 65.6 hours
An Activity's Late Finish date indicates the latest the Activity can finish without delaying a subsequent activity.
Group of answer choices
- True
- False
The purpose of Activity Planning is to ensure that each project team knows when to produce all Deliverables
Group of answer choices
- True
- False
The Early Start of the first Activity on any path (in a Network) must be 1
Group of answer choices
- True
- False
One can use a method called ''forward pass" to add the Early Start and Early Finish for each Activity in each path in your Network Diagram.
Group of answer choices
- True
- False
The mastery of the skills required to manage multiple projects concurrently and competently is referred to as __________.
Group of answer choices
- project management excellence
- project management maturity
- project management conformance
- program management excellence
The sponsor and key stakeholders should participate in the project launch meeting for all of the following purposes EXCEPT:
Group of answer choices
- Discussing resources
- Discussing deliverables
- Discussing schedules
- Discussing contracts
You planned your project to write database application to take one year. The cost of the project is budgeted at $12,500 per month. Six months into the project, you report that the database application is 50% completed and your project has spent $70,000. What is the approximate Estimate at Completion (EAC)?
Group of answer choices
- $150,000
- $140,187
- $142,857
- $137,615
A project is scheduled to last 4 months and cost $300,000. At the end of the first month, the project is 20% complete. What is the Schedule Performance Index (SPI)?
Group of answer choices
- 1.18
- 1.20
- 1.00
- 0.80
A precedence relationship where the completion of an activity depends on the completion of another activity is called a __________.
Group of answer choices
- Start to start dependency
- Finish to finish dependency
- Finish to start dependency
- Start to finish dependency
A precedence relationship where the completion of an activity depends on the completion of another activity is called a __________.
Group of answer choices
- Finish to finish dependency
- Start to start dependency
- Start to finish dependency
- Finish to start dependency
_____ are broken down into _______, which can be further broken down into _______.
Group of answer choices
- Projects, tasks, programs
- Projects, programs, tasks
- Programs, projects, tasks
- Programs, tasks, projects
Step by Step Solution
There are 3 Steps involved in it