Question: The learning rate for a particular operation is 90%, and the first unit of production took 100 hours. What is the number of labor hours

The learning rate for a particular operation is 90%, and the first unit of production took 100 hours.

What is the number of labor hours required to produce the eighth (8th) unit?

Note: you should use the general equation for learning curves to do this problem:

  • TN = T1 x Ln = Time required for the Nth unit, where:
    • TN = unit cost or unit time of the Nth unit
    • L = decimal learning curve rate (e.g., 0.9 for 90% learning rate)
    • n = number of times T is doubled

Group of answer choices

  • 81.0 hours
  • 72.9 hours
  • 41.0 hours
  • 65.6 hours

An Activity's Late Finish date indicates the latest the Activity can finish without delaying a subsequent activity.

Group of answer choices

  • True
  • False

The purpose of Activity Planning is to ensure that each project team knows when to produce all Deliverables

Group of answer choices

  • True
  • False

The Early Start of the first Activity on any path (in a Network) must be 1

Group of answer choices

  • True
  • False

One can use a method called ''forward pass" to add the Early Start and Early Finish for each Activity in each path in your Network Diagram.

Group of answer choices

  • True
  • False

The mastery of the skills required to manage multiple projects concurrently and competently is referred to as __________.

Group of answer choices

  • project management excellence
  • project management maturity
  • project management conformance
  • program management excellence

The sponsor and key stakeholders should participate in the project launch meeting for all of the following purposes EXCEPT:

Group of answer choices

  • Discussing resources
  • Discussing deliverables
  • Discussing schedules
  • Discussing contracts

You planned your project to write database application to take one year. The cost of the project is budgeted at $12,500 per month. Six months into the project, you report that the database application is 50% completed and your project has spent $70,000. What is the approximate Estimate at Completion (EAC)?

Group of answer choices

  • $150,000
  • $140,187
  • $142,857
  • $137,615

A project is scheduled to last 4 months and cost $300,000. At the end of the first month, the project is 20% complete. What is the Schedule Performance Index (SPI)?

Group of answer choices

  • 1.18
  • 1.20
  • 1.00
  • 0.80

A precedence relationship where the completion of an activity depends on the completion of another activity is called a __________.

Group of answer choices

  • Start to start dependency
  • Finish to finish dependency
  • Finish to start dependency
  • Start to finish dependency

A precedence relationship where the completion of an activity depends on the completion of another activity is called a __________.

Group of answer choices

  • Finish to finish dependency
  • Start to start dependency
  • Start to finish dependency
  • Finish to start dependency

_____ are broken down into _______, which can be further broken down into _______.

Group of answer choices

  • Projects, tasks, programs
  • Projects, programs, tasks
  • Programs, projects, tasks
  • Programs, tasks, projects

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!