Question: The likelihood the original critical path ( s ) will change once the project is initiated is referred to as Question 9 Select one: A
The likelihood the original critical paths will change once the project is initiated is referred to as
Question Select one:
A
Flexibility.
B
Resilience.
C
Sensitivity.
D
Concurrent engineering.
E
Rigidity.