Question: The likelihood the original critical path ( s ) will change once the project is initiated is referred to as Question 2 options: flexibility. resilience.
The likelihood the original critical paths will change once the project is initiated is referred to as
Question options: flexibility.
resilience.
sensitivity
concurrent engineering.
rigidity.