Question: The list below has the only 4 paths in a project, along with their respective durations.ACGI 2 3 ADFI 2 0 BDGI 2 3 BEGI
The list below has the only paths in a project, along with their respective durations.ACGI ADFI BDGI BEGI What is the slack time of activity A