Question: The main step in IT project development is efficient activity planning and best effort estimation which can help on time project completion. The following chart
The main step in IT project development is efficient activity planning and best effort estimation which can help on time project completion. The following chart shows project activities dependencies relationships where the allocated completion duration of each activity is provided. You are required to calculate the following times.
(a) Forward Pass from left to right: Early Start and Early Finish times for each task?
(b) Backward Pass from right to left: Late Finish and Late Start times of each task?