Question: The manpower requirement for each activity in a construction project is given below: Activity Activity Duration Manpower Requirement per day 1-2 4 4 1-3 2

The manpower requirement for each activity in a construction project is given below: Activity Activity Duration Manpower Requirement per day 1-2 4 4 1-3 2 3 1-4 3 3 2-4 5 5 3-4 6 3 4-5 2 4 5-6 3 3 2-5 1 6 4-6 4 5 All the activities are scheduled to start at its Earliest Start Times. 1) Draw the project network and determine the critical path and duration 2) Perform Resource Loading and Leveling using a time-scale network. 3) If only 10 men are available for the execution of the project, perform resource allocation
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
