Question: the manpower requirement for each activity in a construction project is given in the attached table. All activities are scheduled to start at it's earliest

the manpower requirement for each activity in a construction project is given in the attached table.

All activities are scheduled to start at it's earliest Start times

1. if only 10 men are available for the execution of the project, perform resource allocation

the manpower requirement for each activity in a

ACTIVITY 1-2 1-3 1-4 2-4 3-4 4-5 5-6 2-5 4-6 Activity Duration (in days) 2 3 6 2 3 Manpower Requirement per day 4 3 3 5 4 3 2