Question: The master must put 5 workers to perform 5 typical operations. From the timekeeping data, it is known how many minutes, on average, each worker
The master must put 5 workers to perform 5 typical operations. From the timekeeping data, it is known how many minutes, on average, each worker spends on each operation. These data are presented in the table1.
Table 1.
| Works
| Workers
| ||||
| A | B | C | D | E | |
| 1 | 10 | 11 | 9 | 12 | 8 |
| 2 | 6 | 8 | 15 | 7 | 5 |
| 3 | 7 | 8 | 10 | 9 | 3 |
| 4 | 5 | 9 | 6 | 6 | 10 |
| 5 | 3 | 4 | 12 | 8 | 2 |
How to distribute workers by operations so that the total cost of working time would be minimal?
Write detailed conclusions.
Write the Table of model elements in MS EXCEL sheet.