Question: the master schedule for A calls for a start quantity of 250 units in week 6. prepare the material plan for item c. no excel
the master schedule for A calls for a start quantity of 250 units in week 6. prepare the material plan for item c.
no excel solutions please
Challenge 2: The Bill of Material for Product A is as follows: A 1 B(1) D(2) 1 C(2) B(1) 1 C(2) The following information about A's components is available: Item B D Quantity Policy Lot for Lot Fixed Q = 1000 Lot for Lot Lead Time (Weeks) 2 1 3 Scheduled Receipts none 1000 in Week 1 none Beginning Inventory 0 200 0 Safety Stock Req's none none The Master Schedule for A calls for a start quantity of 250 units in Week 6. Prepare the material plan for item C. none Expert
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock