Question: The minimum amount of time a dependent activity must be delayed to begin or end is referred to as Question 9 options: hammock. buffer. cushion.

The minimum amount of time a dependent activity must be delayed to begin or end is referred to as Question 9 options: hammock. buffer. cushion. laddering. lag