Question: The Money Pit a . Lower Specification Calculation ( ) ( ) 13.066 5.00 0.64 3 4.21 ?? =

The Money Pit
a. Lower Specification Calculation ( )( )
13.066 5.00 0.64
3 4.21
â?? =
Upper Specification Calculation ( )( )
25.00 13.066 0.94
3 4.21
â?? =
( )min 0.64, 0.94 0.64pkC = =
( )
25 5 0.79
6 4.21
pC â??
= =
b. Because pC and pkC have values less than 1, the process is not capable of meeting
specifications. Yes, valid because the process is under statistical control, as can be
shown by plotting the last 15 observations on control charts. Ask students to
demonstrate that the process is in statistical control.
c. The variability of the process must be greatly reduced. Also, the process should be
better centered between the specification limits.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!