Question: The most common method for shortening project time when resources are not constrained is to: Multiple choice question. assign additional staff and equipment to activities

The most common method for shortening project time when resources are not constrained is to:
Multiple choice question.
assign additional staff and equipment to activities
reducing project scope
outsourcing project work
fast-tracking critical project activities