Question: For the in-line skate example described in Problem 10, design a production line to achieve an output rate of 90 per hour. TaskTime (sec.) 1...........20

For the in-line skate example described in Problem 10, design a production line to achieve an output rate of 90 per hour.
TaskTime (sec.)
1...........20
2...........10
3...........30
4...........10
5...........30
6...........20
7...........10
8...........20

Step by Step Solution

3.46 Rating (169 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

For 90 partshour each station needs to have a work content of 40 sec or less A configurat... View full answer