Question: The most commonly used performance measure for evaluating if work is being completed as planned at any given time point in a project is which
The most commonly used performance measure for evaluating if work is being completed as planned at any given time point in a project is which of the following? Question 17 options: Schedule variance (SV) Cost variance (CV) Neither CV or SV. Both CV and SV