Question: The most cost - effective approach to reducing the project duration by 1 day is: Crash activity A 1 day at a total cost of

The most cost-effective approach to reducing the project duration by 1 day is:
Crash activity A 1 day at a total cost of $4,500
Crash activities A and D1 day each at a total cost of $2,300
Crash activity B 1 day at a total cost of $750
Crash activities C and D 1 day each at a total cost of $1,300
Crash activities D and E 1 day each at a total cost of $800
 The most cost-effective approach to reducing the project duration by 1