Question: The MPC system at a company performs a weekly update of the MPS and MRP production-planning data. At the start of week 1, the MPS
The MPC system at a company performs a weekly update of the MPS and MRP production-planning data. At the start of week 1, the MPS for products A and B are as listed next.

One unit of component C is required to manufacture products A and B. The lead time for C is 1 week, the safety stock is 0, the lot size is 10 units, the on-hand balance of C at the start of week 1 is 15 units, and a scheduled receipt of 10 units of C is due in week 1. Complete the MRP record for component C for the 6 periods, and determine the planned orders, inventory balance, and average inventory level.
Period (weeks) Product A Product B 1 2 3 5 15 0 25 0 0 15 15 0 20 5 10 0 5 6Step by Step Solution