Question: The MPC system at a company performs a weekly update of the MPS and MRP production-planning data. At the start of week 1, the MPS

The MPC system at a company performs a weekly update of the MPS and MRP production-planning data. At the start of week 1, the MPS for products A and B are as listed next.

The MPC system at a company performs a weekly

One unit of component C is required to manufacture products A and B. The lead time for C is 1 week, the safety stock is 0, the lot size is 10 units, the on-hand balance of C at the start of week 1 is 15 units, and a scheduled receipt of 10 units of C is due in week 1. Complete the MRP record for component C for the 6 periods, and determine the planned orders, inventory balance, and average inventory level.

Period (weeks) Product A Product B 1 2 3 5 15 0 25 0 0 15 15 0 20 5 10 0 5 6

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!