Question: ) The net demand for the tables is given below: Week 8 9 10 11 12 13 14 15 16 17 Net Demand 20 25
) The net demand for the tables is given below:
| Week | 8 | 9 | 10 | 11 | 12 | 13 | 14 | 15 | 16 | 17 |
| Net Demand | 20 | 25 | 40 | 12 | 5 | 32 | 24 | 18 | 16 | 30 |
The lead time to receive a leg is 2 weeks. In week 0, there are 10 tables and 30 legs in inventory. It is expected to receive 30 reworked legs in week 10.
- Complete the MRP table below for the legs in the light of the above information.
| Week | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 | 13 | 14 | 15 | 16 | 17 |
| Gross Requirement |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| Net Requirement |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| Time-Phased Net Requirement |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| Planned Order Release (lot for lot) |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|