Question: The network below represents a project being analyzed by Critical Path Methods. Activity durations (time units) are: A=5,B=2,C=12,D=3,E =5,F=1,G=7,H=2,I=10, and J=6. If activity C were
The network below represents a project being analyzed by Critical Path Methods. Activity durations (time units) are: A=5,B=2,C=12,D=3,E =5,F=1,G=7,H=2,I=10, and J=6. If activity C were delayed by two-time units, what would happen to the project duration, will be any impact? Concisely explain your