Question: The network below represents a project being analyzed by the critical path method. Activity durations are A = 5, B = 2, C = 12,
The network below represents a project being analyzed by the critical path method. Activity durations are A = 5, B = 2, C = 12, D = 3, E = 5, F = 1, G = 7, H = 2, I = 10, and J = 6. Based on the information provided above, answer the following question:
1.Identify the critical path
2. What is the overall length of the project?
3. Calculate Es, Ef, LS, LF and Float/slack for all activities
1. The network below represents a project being analyzed by the critical path method. Activity durations are A=5,B=2,C=12,D=3,E=5,F=1,G=7,H=2,I=10, and J=6. Based on the information provided above, answer the following questions; i. Identify the critical path ii. What is the overall length of the project? iii. Calculate ES, EF, LS, LF, and Float/slack for all activitiesStep by Step Solution
There are 3 Steps involved in it