Question: The network below represents a project being analyzed by the critical path method. Activity durations in weeks, are given in the following table and required

The network below represents a project being analyzed by the critical path method. Activity durations in weeks, are given in the following table and required that a the network diagram be drawn: Activity Preceding Duration A -- 9 B A 2 C A 12 D A 5 E B 6 F B 8 G C, F 3 H D 2 I H 8 J G, I 6 K E, J 2 Draw the network diagram. Which activities form the critical path? How much slack exists at activities A and F? What is the duration of the critical path?