Question: The network below.represents a project being analyzed by the critical . , G=7, H-2, 1-10, and J 6. a. What task must be on the


The network below.represents a project being analyzed by the critical . , G=7, H-2, 1-10, and J 6. a. What task must be on the critical path, regardless of activity durations? b. What is the duration of path A-B-E-H-J? c. What is the critical path of this network? d. What is the length of the critical path? e. What is slack time at activity 11? f. What is the Late Finish of activity H? g. If activity C were delayed by two-time units, what would happen to the project duration? E 5 B H A 2 2 5 Start J 12 F 10 1
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
