Question: The network diagram and task times for a project are shown below. A A4 A3 Task A1 A2 Duration (days) 9 2 1 A3 A4

The network diagram and task times for a project

The network diagram and task times for a project are shown below. A A4 A3 Task A1 A2 Duration (days) 9 2 1 A3 A4 9 A5 8 What is the slack for activity Az? 22 days