Question: The network diagram below shows six tasks required to complete a project and the associated times for those tasks. A flowchart showing tasks A through
The network diagram below shows six tasks required to complete a project and the associated times for those tasks.
A flowchart showing tasks A through F with duration.From start to task A weeks. Task A to task B weeks and task A to task C weeks. Task B to task D weeks and task B to task E and task C to task E weeks. Task D and task E to task F week.
Which of the following identifies the critical path tasks?
Multiple Choice
A B D F
A B C D E F
A C E F
A B E F