Question: The network diagram below shows the tasks required to complete a project and the associated times for those tasks. Which task has the greatest amount
The network diagram below shows the tasks required to complete a project and the associated times for those tasks. Which task has the greatest amount of slack?
diagram shows task A weeks preceeds B and C ; D follows B; E follows B and C; F follows D and E
Picture
Group of answer choices
Activity E
Task A
Task C
Task F
Task D
Task B