Question: The new process will need more machines that their current level of two. They are currently running 16 hours a day, 6 days a week,
The new process will need more machines that their current level of two. They are currently running 16 hours a day, 6 days a week, for 50 weeks per year. If they use a capacity cushion of 20%, how many more machines will the need to purchase