Question: The new process will need more machines that their current level of two. They are currently running 16 hours a day, 6 days a week,
The new process will need more machines that their current level of two. They are currently running 16 hours a day, 6 days a week, for 50 weeks per year. If they use a capacity cushion of 20%, how many more machines will the need to purchase? p d q s 0.01 1,000,000 200 1
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
